MALABA WATER SUPPLY PROJECT LOT 1

Contract value: 654 million

Financier: African Development Bank

Contractor: Zhongmei Engineering Group

Expected completion date: June 2022

Project Area: Teso North

Scope

  • Construct 11km new gravity intake
  • Construct 11.5km new raw water gravity main DN500
  • Construct a horizontal treatment plant of capacity 6,000m3/day, complete with associated works.
  • Rehabilitate existing water treatment units with their associated works to take them to their combined capacity of 2,150m3/day.
  • Rehabilitate existing staff houses.
  • Rehabilitate existing 100m3 masonry backwash tank.
  • Rehabilitate 24.5km treated water gravity main to Malaba through Kimaeti, Kocholia and Amagoro (diameter ranging from 350-250mm).
  • Rehabilitate 10km treated water gravity main to Angurai DN250-100mm UPVC and GI.
  • New distribution pipelines of DN150-75mm in steel and UPVC length approximately 20km to serve Myanga, Kokare, Kamuriai/Jairos, Angurai, Chamasir, Netima, Malakisi, Amoni and Ndakaru.
  • Rehabilitate storage tanks at Koteko Hills, Kocholia, Kokare, Angurai, Mwari Hills and Akoreti Hills.
  • Construct new storage tank at Kimaeti (225m3).
  • Construct communal water points (water kiosks) – 7 no.
  • Rehabilitate Kakoli Spring intake.

Luctus nec ullamcorper mattis, pulvinar dapibus leo. Proin gravida nibh vel velit auctor aliquet

MALABA SANITATION PROJECT LOT 2

Contract value: 306 million

Financier: African Development Bank

Contractor: Stecol Corporation

Expected completion date: June 2021

Project Area: Teso North, Malaba

Scope

  • 16km long main trunk sewer lines (200-600mm diameter HDPE pipes)
  • 2km long smaller tributary sewer lines (200mm diameter HDPE pipes)
  • Treatment works (preliminary treatment system, 3 anaerobic ponds, 3 facultative ponds and 6 maturation ponds)
  • 4 ablution blocks
  • Office block and staff houses

DTF PROJECT

Contract value: 10.5 million

Financier: Water Sector Trust Fund

Contractor: Jerosilicon Construction Company Limited

Expected completion date: 31st May, 2021

Project area: Port Victoria, Bunyala

Scope

The DTF (decentralized treatment facility) comprises of six modules: receiving bay/balancing tank, sludge drying bed, anaerobic reactor, wetlands, solid waste incinerator and operator’s office.